28 April 2023
By the 15th April, the construction of the fifth level of the premises was completed. Furthermore, the air conditioning system was installed on the ground floor and the second level. The ground floor saw several works being completed including the water and electricity, aluminium, plastering and tiling. Aluminium was also installed on Level 1, while water and electricity installation as well as tiling were done on Level 2 of the premises. Plastering works on the outdoor façade was also initiated and will continue progressing over the following months.