During the month of July, work continued mainly focused on finishings and also furnishing of the premises. Air conditioning, water,…

Progress

Finishings of the premises continued during the month of June with air conditioning as well as water and electricity being…

Progress

In May construction works were completed, with the focus now shifting fully to the finishing and furnishing of the premises….

Progress

By the 15th April, the construction of the fifth level of the premises was completed. Furthermore, the air conditioning system…

Progress

By the 15th March the fourth level of the premises was constructed. Water and electricity were installed on the ground…

Progress

By the 15th February the construction on Level 3 was completed. Additionally, water, electricity and piping for air conditioning units…

Progress

Water, electricity and piping for air conditioning units were installed on the first floor of the premises.