Our Progress
Porziuncola by Golden Care is being developed thanks to an investment by a team of multidisciplinary professionals in the sector all with the scope of delivering a holistic patient centred care model that respects the client’s experience, values, needs and preferences in the planning, co-ordination, and delivery of care. Below you can find a timeline showcasing the latest progress in the development of this new care home.Porziuncola Works Timeline
Timeline | Milestone | Floor |
---|---|---|
July - December 2022 | Construction | Level 0, 1 and 2 |
15th Feb 2023 | Construction | Level 3 |
15th March 2023 | Construction | Level 4 |
15th April 2023 | Construction | Level 5 |
January 2023 | Water & Electricity | Level 1 |
February 2023 | Water & Electricity | Level 2 |
March 2023 | Water & Electricity | Level 0 |
February 2023 | Plastering | Level 1 |
March 2023 | Plastering | Level 2 |
March 2023 | Plastering | Outside Façade |
February - mid March 2023 | Tiling | Level 1 - complete |
February - mid March 2023 | Tiling | Level 2 - commenced |
January 2023 | Piping and Preparation of Airconditioning | Level 1 |
February 2023 | Piping and Preparation of Airconditioning | Level 2 and 50% of level 3 |
March 2023 | Piping and Preparation of Airconditioning | Level 3 and to start level 4 |