Our Progress

Porziuncola by Golden Care is being developed thanks to an investment by a team of multidisciplinary professionals in the sector all with the scope of delivering a holistic patient centred care model that respects the client’s experience, values, needs and preferences in the planning, co-ordination, and delivery of care. Below you can find a timeline showcasing the latest progress in the development of this new care home.

Porziuncola Works Timeline

Timeline

MilestoneFloor

July - December 2022

Construction

Level 0, 1 and 2

15th Feb 2023Construction

Level 3

15th March 2023Construction

Level 4

15th April 2023Construction

Level 5

January 2023

Water & Electricity

Level 1

February 2023

Water & Electricity

Level 2

March 2023

Water & Electricity

Level 0

February 2023

Plastering

Level 1

March 2023

Plastering

Level 2

March 2023

PlasteringOutside Façade

February - mid March 2023

Tiling

Level 1 - complete

February - mid March 2023

Tiling

Level 2 - commenced

January 2023

Piping and Preparation of Airconditioning

Level 1

February 2023

Piping and Preparation of Airconditioning

Level 2 and 50% of level 3

March 2023

Piping and Preparation of Airconditioning

Level 3 and to start level 4